Description of the Works
This is the second visit of four to maintain the fire alarm systems this testing year (October - September). Access will be required to all areas of the building (unless stated below) (with keys normally obtained from E&FM).
The testing will be silent and the fire panel regularly monitored by BTS. No outputs on the system will be activated during the work.
(Ground floor already completed - access requirements on this floor will be minimal)
Timescale
05.03.25
07:30 – 10:00 – Sir Frank Gibb Teaching
10:00 – 12:00 – Sir Frank Gibb Labs
13:00 – 15:00 – John Pickford
How can I get more information and help?
The Estates and Facilities Management team member looking after the task is detailed below and can be contacted about any difficulties experienced because of these works.
Edward Roe - Fire Alarm Engineer for BTS
Mobile: 07884237879
Email: Edward@buildingtechnologyservices.co.uk